New Connection / Extension In Load
5.6.1
Estimating
Charges for new and additional supply.
As
soon as the application on the prescribed form as per the Sales Manual is
received in the Sub Division for provision of supply or additional supply, the
Senior Assistant (Com.) shall take the following actions:
(a)
Complete details of the prospective consumer, as well as the load
applied for, shall be furnished to the J.E. in charge of the Section for
submitting the estimate/report for provision of supply in respect of general
services and LT connections with connected load up to 20 kW. For loads between
21 – 50 kW the S.D.O., for loads between 51 – 100 KW the Sr. Executive
Engineer, and for loads above 100 KW the S.E., shall visit the site, assess the
maximum demand of the prospective consumer, propose the works to be erected for
providing the supply in accordance with the distribution policy of the HPSEB and
submit the estimate to the competent authority for sanction within 7 days. In
case of HT supply with load above 100 KW, the S.E. shall be responsible for
making commercial assessment of the case and take further action as required.
(b)
The S.D.O. shall issue the Demand Notice within the stipulated period,
reckoned from the date of receipt of the application in the Sub Division.
For supplies with connected load of more than 50 KW the estimate shall be
submitted to the Sr. Ex. Engineer who shall return the estimate duly sanctioned
to the S.D.O. within 7 days. Sanctions
for the estimates for HT supplies with load above 100 KW shall be obtained
through personal follow up from the competent authority as per provision of
Sales Manual, and returned to the concerned S.D.O. for issue of Demand Notice.
(c)
S.D.O. in charge of the Sub Division shall issue the Demand Notice
within the stipulated period reckoned from the date of the receipt of the
application in the Sub Division.
(d)
In case the Demand Notice is not received by the prospective consumer
within 30 days of the date of application, he may lodge a complaint on Form-IV
with the officer indicated in Col.(3) of Table 5.6 below. The concerned officer
shall take an immediate action to ensure that the Demand Notice is issued.
However, if the Demand Notice is not received by the prospective consumer within
45 days of the date of application, he may lodge complaint on Form-V with
the officer indicated in Col.(4) of Table 5.6 below, who shall acknowledge the
complaint and take necessary action in the matter without further loss of time.
(e) The S.D.O./Sr. Executive Engineer/S.E./C.E. shall investigate the delays in furnishing the estimate to the prospective consumer beyond the stipulated period with a view to fix the responsibility and submit the report on Form-VIIIF to the next higher officer within 30 days by associating the prospective consumer in the investigation.
View Page Wise:
|1|2|3|4|5|6|7|8|9|10|11|12|13|14|15|16|17|18|19|20|21|22|23|24|25|26|27|28|29|30|31|32|
( Any Page of the report can also be visited directly by typing www.hpseb.com/CX.htm in Address Bar, where XX is actual page number eg. www.hpseb.com/C1.htm )
History | Organization | Achievements &
Milestones | Hydro
Potential
Invest in Hydro
| Mission | Hydro Policy | Tenders
|Tariff | Precautions | Photo Gallery | Feedback | Contact | HOME