HIMACHAL PRADESH STATE ELECTRICITY BOARD                     

Click Here to Download Complete Notification(19 Pages)

 

ABRIDGED CONDITIONS OF SUPPLY

(Applicable to consumers of H.P.S.E.B.)   

(k)                   Industrial Supply  shall mean a supply for Industrial, Agricultural, Irrigation and pumping purposes. 

(l)            Month shall mean a billing month. 

(m)            Power Factor  shall mean the ratio expressed as a percentage of the kilowatt to the kilovolt amperes supplied during any period.  The power factor shall be calculated upto two decimal places. 

(n)            Point of commencement of supply:  the point of commencement of supply of energy to a consumer shall be deemed to be the point at the outgoing terminals of the cutouts inserted by the Board in each conductor of every service line other than an earthed or earthed neutral conductor or the earthed external conductor of a concentric cable at the consumers premises. 

(o)            Declared voltage:  Himachal Pradesh State Electricity Board has adopted alternating current system at 50 cycles per second at the following pressures: 

 Pressure                      Declared voltage                Remarks 

Low (Single phase)                 230 volts                Phase to Neutral 

Medium (Three phase)           400 volts                Between phases

High (Three phase)                 2,200 volts             Between phases

                                                  11,000 volts           Between phases

                                                  15,000 volts           Between phases

                                                  22,000 volts           Between phases

                                                  33,000 volts            Between phases

                                                  66,000 volts            Between phases

                                                  1,32,000 volts         Between phases

                                                  2,20,000 volts         Between phases 

(p)            Service Line means an electric supply line through which energy is or is intended to be supplied to the consumer either from Boards mains, sub-mains or immediately from the sub-station. 

(q)            The Rules shall mean the Indian Electricity Rules,1956 as amended from time to time.  

(r)             Commissionshall mean the Himachal Pradesh State Electricity Regulatory Commission.

(s)             Sanctioned Load:  shall mean load in KW for which the Board has agreed to supply from time to time subject to governing terms and conditions.  The total connected load is required to be sanctioned from the competent authority. 

(t)              Consumer Service Charges:  shall mean the fixed amount to be paid by the consumer as defined in the respective tariff schedule. 

(u)              Schedule:  shall mean the Tariff Schedule as amended from time to time.

    (Any Page of the petition can also be visited directly by typing www.hpseb.com/acs/axx.htm in Addr. Bar, where XXX is actual page number eg. www.hpseb.com/acs/a12.htm )  

Click Here to Download Complete Notification19 Pages)