Name of Transmission Licensee:-    Transmission Wing.
Project-wise / Scheme-wise Capital Expenditure (New Projects & CWIP) FOR THE YEAR 2005-06 Form No: F15
(Rs. In Crore)
Sr. Name of Project/ Project Cost Reason Projected Schedule Reasons Expdt. Expdt. Interest Deductions/ Transfer Source
No. Scheme. Original estimate Revised estimate for cost Original completion date Revised completion date  for delay* up to during during Transfers  to Fixed of Captial
        revision       the end of the year Construction   Assets Institution
                preceding       (Interest + wise
                 year       expenses amount
                        capitalized) available
A Generation Scheme.                        
1 Prov. Pot head yard at 1.05 ----- ----- 3/06 ----- ----- 1.73 0.42 0.13 ----- ----- Gen.
  Largi HEP. PFC-0.65                      
    SP-0.40                      
2 Prov. Terminal equipment 0.39 ----- ----- 3/06 ----- ----- 0.23 ----- ----- ----- ----- Gen.
  at 33/11kV S/Stn. at                        
  Shapur against Khauli                        
  H.E.P.                        
                           
3 C/O 132 kV D/C T/L line from 16.04 32.61 Due to cost escalation  ----- 3/06 Change in connectivity from 41.59 8.17 10.08 ----- ----- PFC-
  Larji to Kangoo.     of material & labour.     Hamirpur to Kangoo and late           SP-
              delivery of material.            
B Deposit with HPJVNL                        
1 Uhal Stage - iii 5.20 14.04 Original scheme 3/05 8/06 Scheme cleared by CEA 2.18 0.40 0.13 ----- ----- PFC-
        sanctioned during     during 9/02 and scheme           SP-
        2/91 & later on     undertaking for preliminary            
        cleared by CEA     activities during 2002-03.            
        during 9/02.                  
                           
2 220 kV Trans. Line 23.94 ----- ----- 3/05 3/07 Work awarded on turn-key 5.82 4.99 1.37 ----- ----- PFC-
  Kashang to Bhaba. PFC         basis during 6/05           SP-
   
                     
C Survey & Investigation.                      
1 Detailed survey of 220kV line                        
  from                        
I) Kuther to Chamera-III. ----- ----- ----- 3/06 8/06 Delayed by contractor. 0.05 0.05 ----- ----- ----- S & I (SP)
ii) Survey of 220kV D/C line from ----- ----- ----- 3/06 3/07 Survey work was completed 0.19 0.05 0.0007 ----- ----- S & I (SP)
  Swara Kuddu to Moginand.           but due to change of line            
              route via Uttranchal, job            
D(I) State Plan(T&D)(Ongoing Schemes).           delayed.            
                           
1 220kV S/C Trans. Line from 10.24 ----- Due to cost escalation  11/2000 Commissioned ----- 16.54 0.03 1.48 ----- ----- SP
  Thein to Jassure a/w terminal SP-4.54   of materials & labour.   during 3/01              
  bay at Jassure. PFC-5.70                      
                           
2 Aug. of 132/33 kV, 2x9 1.89 ----- ----- 3/05 3/06 ----- 1.65 0.29 ----- ----- ----- SP
  MVA T/F to 2x16 MVA,         1 No. T/F              
  132/33 kV Sub-Station         commissioned              
  at Kangra.         during 11/05              
Contd/-2
-2-
Sr. Name of Project/ Project Cost Reason Projected Schedule Reasons Expdt. Expdt. Interest Deductions/ Transfer Source
No. Scheme. Original estimate Revised estimate for cost Original completion date Revised completion date  for delay* up to during during Transfers  to Fixed of Captial
        revision       the end of the year Construction   Assets Institution
                preceding       (Interest + wise
                 year       expenses amount
                        capitalized) available
                           
3 Unified load despatch 7.89 21.59 Cost escalation in 11/2000 Commissioned ----- 20.30 3.56 6.24 ----- ----- SP-
  centre(SLDC) SP-3.59 SP-12.09 material, Estt. &   during 8/01             WB-
    WB-4.30 WB-9.50 labour components &                  
        non provision of IDC                  
                           
4 C/O 220kV S/C line from Dehar 26.65 ----- -do- ----- Commissioned ----- 28.58 4.25 4.25 ----- ----- SP & Dep.
  P/H to Kangoo a/w 220/132kV                        
  1x80 MVA S/Stn. at Kangoo.                        
                           
5 C/O 220/132kV S/Stn. 18.47 ----- -do- ----- Commissioned ----- 21.05 0.04 0.04 ----- ----- SP & PGCIL
  Mattansidh.         during 8/01              
                           
6 Inst. Of 10 MVA, 66/22kV 2.29 ----- -do- ----- ----- ----- 4.10 0.16 0.69 ----- ----- SP & PFC
  S/Phase T/F at 66kV interlinking SP-1.01                      
  S/Stn. at Nogli. PFC-1.28                      
                           
7 Prov. Addl.16 MVA, 2.05 3.10 -do- 12/01 Commissioned Non-avilability of T/F as 4.85 1.71 1.60 ----- ----- SP-
  132/11 kV T/F at SP-0.07       during 4/04 validity of T/F expired. Fresh           PFC-
  Kala-Amb. PFC-1.28         tender were floated.            
    DPT-0.70                      
                           
8 Prov. Addl.16 MVA, 1.50 2.63 -do- 3/01 Commissioned T/F were to be spared from 2.61 (-) 0.01 0.13 ----- ----- SP-
  132/11 kV T/F at Paonta. SP-0.55       during 5/04 Solan which were spared           PFC-
    PFC-0.95         late due to late receipt of T/F            
              & S/Stn. Str. Of Solan.            
                           
9 220 kV S/C line from 10.28 17.06 Due to cost escalation  11/87 9/89 T-35 falling in flood zone to 17.06 ----- 3.14 ----- ----- SP
  Khodri to Majri (1st Ckt.) (SP) (SP) of material & labour.     be shifted. Pending due to            
              abonding of work by two            
              contractor.            
                           
                           
10 220 kV S/C line from 1.90 ----- Due to cost escalation  11/89 3/07 Due to non-availability of 9.70 ----- 1.72 ----- ----- SP
  Khodri to Majri (2nd Ckt.) (SP)   of material & labour.     budget in SP during            
              1999-2000, 2000-01 &            
              2001-02 approval of            
              extension in control room &            
              yard not granted by            
              Uttranchal utility yet.            
                          Contd/-3
-3-
Sr. Name of Project/ Project Cost Reason Projected Schedule Reasons Expdt. Expdt. Interest Deductions/ Transfer Source
No. Scheme. Original estimate Revised estimate for cost Original completion date Revised completion date  for delay* up to during during Transfers  to Fixed of Captial
        revision       the end of the year Construction   Assets Institution
                preceding       (Interest + wise
                 year       expenses amount
                        capitalized) available
                           
11 Aug. of 132/11kV, 16 MVA T/F 8.47 ----- ----- 4/99 Commissioned ----- 10.56 0.08 2.33 ----- ----- SP-
  to 132/33kV, 50 MVA T/F at SP-3.17       during 8/03             PFC-
  Solan & Instl. Of 2x20 MVA PFC-5.30                      
  33/11kV S/Stn. at Solan.                        
                           
12 400 kV S/C line from 75.73 ----- ----- ----- ----- Stay imposed by HPERC on 15.10 4.41 3.03 ----- ----- SP-
  Nalagarh to Kunihar a/w SP-30.23         all activities.           PFC-
  2x315 MVA, 400/220/132 PFC-45.50                      
  kV S/Stn.at Kunihar.                        
                           
13 66kV S/C line from Gumma to 9.32 ----- Due to escalation of 5/99 Commissioned ----- 23.02 3.39 7.97 ----- ----- SP-
  Hulli(Kotkhai) a/w 2x6 MVA SP-3.82   material & labour.   during 6/01             PFC-
  S/Stn. at Hulli. PFC-5.50                      
                           
14 220/66 kV,2x80/100 17.12 ----- ----- 3/06 Commissioned ----- 38.00 7.57 2.61 ----- ----- SP-
  MVA, S/Stn. at Baddi. SP-2.12       during 2/05 &             REC-
    REC-15.00  </