|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Name
of Transmission Licensee:-
Transmission Wing. |
|
|
|
|
| Project-wise
/ Scheme-wise Capital Expenditure (New Projects & CWIP) |
|
|
FOR THE YEAR 2005-06 |
|
|
Form No: F15 |
|
|
|
|
|
|
(Rs. In Crore) |
|
| Sr. |
Name of Project/ |
Project Cost |
Reason
|
Projected Schedule |
Reasons |
Expdt.
|
Expdt.
|
Interest |
Deductions/ |
Transfer |
Source
|
|
| No. |
Scheme. |
Original
estimate |
Revised estimate |
for cost |
Original
completion date |
Revised
completion date |
for delay* |
up
to |
during
|
during
|
Transfers |
to Fixed |
of Captial |
|
| |
|
|
|
revision |
|
|
|
the end of |
the year |
Construction |
|
Assets |
Institution |
|
| |
|
|
|
|
|
|
|
preceding |
|
|
|
(Interest + |
wise
|
|
| |
|
|
|
|
|
|
|
year |
|
|
|
expenses
|
amount |
|
| |
|
|
|
|
|
|
|
|
|
|
|
capitalized) |
available |
|
| A |
Generation Scheme. |
|
|
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Prov.
Pot head yard at |
1.05 |
----- |
----- |
3/06 |
----- |
----- |
1.73 |
0.42 |
0.13 |
----- |
----- |
Gen. |
|
| |
Largi HEP. |
PFC-0.65 |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
SP-0.40 |
|
|
|
|
|
|
|
|
|
|
|
|
| 2 |
Prov. Terminal equipment |
0.39 |
----- |
----- |
3/06 |
----- |
----- |
0.23 |
----- |
----- |
----- |
----- |
Gen. |
|
| |
at
33/11kV S/Stn. at |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Shapur
against Khauli |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
H.E.P. |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 3 |
C/O
132 kV D/C T/L line from |
16.04 |
32.61 |
Due
to cost escalation |
----- |
3/06 |
Change
in connectivity from |
41.59 |
8.17 |
10.08 |
----- |
----- |
PFC- |
|
| |
Larji to Kangoo. |
|
|
of material
& labour. |
|
|
Hamirpur to Kangoo and late |
|
|
|
|
|
SP- |
|
| |
|
|
|
|
|
|
delivery of
material. |
|
|
|
|
|
|
|
| B |
Deposit with HPJVNL |
|
|
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Uhal Stage - iii |
5.20 |
14.04 |
Original
scheme |
3/05 |
8/06 |
Scheme
cleared by CEA |
2.18 |
0.40 |
0.13 |
----- |
----- |
PFC- |
|
| |
|
|
|
sanctioned during |
|
|
during 9/02 and scheme |
|
|
|
|
|
SP- |
|
| |
|
|
|
2/91 & later on |
|
|
undertaking for preliminary |
|
|
|
|
|
|
|
| |
|
|
|
cleared by CEA |
|
|
activities
during 2002-03. |
|
|
|
|
|
|
|
| |
|
|
|
during 9/02. |
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 2 |
220 kV Trans. Line |
23.94 |
----- |
----- |
3/05 |
3/07 |
Work
awarded on turn-key |
5.82 |
4.99 |
1.37 |
----- |
----- |
PFC- |
|
| |
Kashang
to Bhaba. |
PFC |
|
|
|
|
basis during
6/05 |
|
|
|
|
|
SP- |
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| C |
Survey & Investigation. |
|
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Detailed survey of 220kV line |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
from |
|
|
|
|
|
|
|
|
|
|
|
|
|
| I) |
Kuther to Chamera-III. |
----- |
----- |
----- |
3/06 |
8/06 |
Delayed by contractor. |
0.05 |
0.05 |
----- |
----- |
----- |
S & I (SP) |
|
| ii) |
Survey of 220kV D/C line from |
----- |
----- |
----- |
3/06 |
3/07 |
Survey
work was completed |
0.19 |
0.05 |
0.0007 |
----- |
----- |
S & I (SP) |
|
| |
Swara Kuddu to Moginand. |
|
|
|
|
|
but
due to change of line |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
route
via Uttranchal, job |
|
|
|
|
|
|
|
| D(I) |
State Plan(T&D)(Ongoing Schemes). |
|
|
|
|
|
delayed. |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 1 |
220kV
S/C Trans. Line from |
10.24 |
----- |
Due
to cost escalation |
11/2000 |
Commissioned |
----- |
16.54 |
0.03 |
1.48 |
----- |
----- |
SP |
|
| |
Thein to Jassure a/w terminal |
SP-4.54 |
|
of materials & labour. |
|
during 3/01 |
|
|
|
|
|
|
|
|
| |
bay at Jassure. |
PFC-5.70 |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 2 |
Aug. of 132/33 kV, 2x9 |
1.89 |
----- |
----- |
3/05 |
3/06 |
----- |
1.65 |
0.29 |
----- |
----- |
----- |
SP |
|
| |
MVA
T/F to 2x16 MVA, |
|
|
|
|
1 No. T/F |
|
|
|
|
|
|
|
|
| |
132/33
kV Sub-Station |
|
|
|
|
commissioned |
|
|
|
|
|
|
|
|
| |
at Kangra. |
|
|
|
|
during 11/05 |
|
|
|
|
|
|
|
|
|
|
|
|
|
Contd/-2 |
|
|
|
|
|
|
|
|
|
|
|
-2- |
|
| Sr. |
Name of Project/ |
Project Cost |
Reason
|
Projected Schedule |
Reasons |
Expdt.
|
Expdt.
|
Interest |
Deductions/ |
Transfer |
Source
|
|
| No. |
Scheme. |
Original
estimate |
Revised estimate |
for cost |
Original
completion date |
Revised
completion date |
for delay* |
up
to |
during
|
during
|
Transfers |
to Fixed |
of Captial |
|
| |
|
|
|
revision |
|
|
|
the end of |
the year |
Construction |
|
Assets |
Institution |
|
| |
|
|
|
|
|
|
|
preceding |
|
|
|
(Interest + |
wise
|
|
| |
|
|
|
|
|
|
|
year |
|
|
|
expenses
|
amount |
|
| |
|
|
|
|
|
|
|
|
|
|
|
capitalized) |
available |
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 3 |
Unified
load despatch |
7.89 |
21.59 |
Cost
escalation in |
11/2000 |
Commissioned |
----- |
20.30 |
3.56 |
6.24 |
----- |
----- |
SP- |
|
| |
centre(SLDC) |
SP-3.59 |
SP-12.09 |
material,
Estt. & |
|
during 8/01 |
|
|
|
|
|
|
WB- |
|
| |
|
WB-4.30 |
WB-9.50 |
labour components & |
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
non provision of IDC |
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 4 |
C/O 220kV S/C line from Dehar |
26.65 |
----- |
-do- |
----- |
Commissioned |
----- |
28.58 |
4.25 |
4.25 |
----- |
----- |
SP & Dep. |
|
| |
P/H to Kangoo a/w 220/132kV |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
1x80 MVA S/Stn. at Kangoo. |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 5 |
C/O
220/132kV S/Stn. |
18.47 |
----- |
-do- |
----- |
Commissioned |
----- |
21.05 |
0.04 |
0.04 |
----- |
----- |
SP & PGCIL |
|
| |
Mattansidh. |
|
|
|
|
during 8/01 |
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 6 |
Inst. Of 10 MVA, 66/22kV |
2.29 |
----- |
-do- |
----- |
----- |
----- |
4.10 |
0.16 |
0.69 |
----- |
----- |
SP & PFC |
|
| |
S/Phase T/F at 66kV interlinking |
SP-1.01 |
|
|
|
|
|
|
|
|
|
|
|
|
| |
S/Stn. at Nogli. |
PFC-1.28 |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 7 |
Prov.
Addl.16 MVA, |
2.05 |
3.10 |
-do- |
12/01 |
Commissioned |
Non-avilability
of T/F as |
4.85 |
1.71 |
1.60 |
----- |
----- |
SP- |
|
| |
132/11 kV T/F at |
SP-0.07 |
|
|
|
during 4/04 |
validity of T/F expired. Fresh |
|
|
|
|
|
PFC- |
|
| |
Kala-Amb. |
PFC-1.28 |
|
|
|
|
tender were floated. |
|
|
|
|
|
|
|
| |
|
DPT-0.70 |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 8 |
Prov.
Addl.16 MVA, |
1.50 |
2.63 |
-do- |
3/01 |
Commissioned |
T/F were to be spared from |
2.61 |
(-) 0.01 |
0.13 |
----- |
----- |
SP- |
|
| |
132/11 kV T/F at Paonta. |
SP-0.55 |
|
|
|
during 5/04 |
Solan
which were spared |
|
|
|
|
|
PFC- |
|
| |
|
PFC-0.95 |
|
|
|
|
late due to late receipt of T/F |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
& S/Stn. Str. Of Solan. |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 9 |
220 kV
S/C line from |
10.28 |
17.06 |
Due
to cost escalation |
11/87 |
9/89 |
T-35 falling in flood zone to |
17.06 |
----- |
3.14 |
----- |
----- |
SP |
|
| |
Khodri to Majri (1st Ckt.) |
(SP) |
(SP) |
of material
& labour. |
|
|
be shifted. Pending due to |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
abonding
of work by two |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
contractor. |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 10 |
220 kV
S/C line from |
1.90 |
----- |
Due
to cost escalation |
11/89 |
3/07 |
Due
to non-availability of |
9.70 |
----- |
1.72 |
----- |
----- |
SP |
|
| |
Khodri to Majri (2nd Ckt.) |
(SP) |
|
of material
& labour. |
|
|
budget
in SP during |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
1999-2000,
2000-01 & |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
2001-02
approval of |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
extension
in control room & |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
yard
not granted by |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
Uttranchal utility yet. |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
Contd/-3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
-3- |
|
| Sr. |
Name of Project/ |
Project Cost |
Reason
|
Projected Schedule |
Reasons |
Expdt.
|
Expdt.
|
Interest |
Deductions/ |
Transfer |
Source
|
|
| No. |
Scheme. |
Original
estimate |
Revised estimate |
for cost |
Original
completion date |
Revised
completion date |
for delay* |
up
to |
during
|
during
|
Transfers |
to Fixed |
of Captial |
|
| |
|
|
|
revision |
|
|
|
the end of |
the year |
Construction |
|
Assets |
Institution |
|
| |
|
|
|
|
|
|
|
preceding |
|
|
|
(Interest + |
wise
|
|
| |
|
|
|
|
|
|
|
year |
|
|
|
expenses
|
amount |
|
| |
|
|
|
|
|
|
|
|
|
|
|
capitalized) |
available |
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 11 |
Aug. of 132/11kV, 16 MVA T/F |
8.47 |
----- |
----- |
4/99 |
Commissioned |
----- |
10.56 |
0.08 |
2.33 |
----- |
----- |
SP- |
|
| |
to 132/33kV, 50 MVA T/F at |
SP-3.17 |
|
|
|
during 8/03 |
|
|
|
|
|
|
PFC- |
|
| |
Solan & Instl. Of 2x20 MVA |
PFC-5.30 |
|
|
|
|
|
|
|
|
|
|
|
|
| |
33/11kV S/Stn. at Solan. |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 12 |
400 kV S/C line from |
75.73 |
----- |
----- |
----- |
----- |
Stay
imposed by HPERC on |
15.10 |
4.41 |
3.03 |
----- |
----- |
SP- |
|
| |
Nalagarh
to Kunihar a/w |
SP-30.23 |
|
|
|
|
all activities. |
|
|
|
|
|
PFC- |
|
| |
2x315
MVA, 400/220/132 |
PFC-45.50 |
|
|
|
|
|
|
|
|
|
|
|
|
| |
kV S/Stn.at Kunihar. |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 13 |
66kV
S/C line from Gumma to |
9.32 |
----- |
Due to escalation of |
5/99 |
Commissioned |
----- |
23.02 |
3.39 |
7.97 |
----- |
----- |
SP- |
|
| |
Hulli(Kotkhai)
a/w 2x6 MVA |
SP-3.82 |
|
material & labour. |
|
during 6/01 |
|
|
|
|
|
|
PFC- |
|
| |
S/Stn. at Hulli. |
PFC-5.50 |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 14 |
220/66
kV,2x80/100 |
17.12 |
----- |
----- |
3/06 |
Commissioned |
----- |
38.00 |
7.57 |
2.61 |
----- |
----- |
SP- |
|
| |
MVA, S/Stn. at Baddi. |
SP-2.12 |
|
|
|
during
2/05 & |
|
|
|
|
|
|
REC- |
|
| |
|
REC-15.00 |
|