|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Name
of Transmission Licensee:-
Transmission Wing. |
|
|
|
|
| Project-wise
/ Scheme-wise Capital Expenditure (New Projects & CWIP) |
|
|
FOR THE YEAR 2006-07 |
|
|
Form No: F15 |
|
|
|
|
|
|
(Rs. In Crores). |
|
| Sr. |
Name of Project/ |
Project Cost |
Reason
|
Projected Schedule |
Reasons |
Expdt.
|
Expdt.
|
Interest |
Deductions/ |
Transfer |
Source
|
|
| No. |
Scheme. |
Original
estimate |
Revised estimate |
for cost |
Original
completion date |
Revised
completion date |
for delay* |
up
to |
during
|
during
|
Transfers |
to Fixed |
of Captial |
|
| |
|
|
|
revision |
|
|
|
the end of |
the year |
Construction |
|
Assets |
Institution |
|
| |
|
|
|
|
|
|
|
preceding |
|
|
|
(Interest + |
wise
|
|
| |
|
|
|
|
|
|
|
year |
|
|
|
expenses
|
amount |
|
| |
|
|
|
|
|
|
|
|
|
|
|
capitalized) |
available |
|
| A |
Generation Scheme. |
|
|
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Prov.
Pot head yard at |
----- |
----- |
----- |
3/06 |
6/06 |
Commissioned during 8/06. |
1.87 |
0.14 |
----- |
----- |
----- |
Gen. |
|
| |
Largi HEP. |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 2 |
Prov. Terminal equipment |
0.39 |
----- |
Addl.
2 Nos. 33kV bays |
3/06 |
8/06 |
2
Nos. 33kV bay at Shahpur |
0.93 |
0.7 |
----- |
----- |
----- |
Gen. |
|
| |
at
33/11kV S/Stn. at |
|
|
being
created at Shahpur |
|
|
completed
& 2 No. one each |
|
|
|
|
|
|
|
| |
Shapur & Kangra against
Khauli |
|
|
& Kangra. |
|
|
at
Shahpur & Kangra under |
|
|
|
|
|
|
|
| |
H.E.P. |
|
|
|
|
|
progress. |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 3 |
C/O
132 kV D/C T/L line from |
16.04 |
32.61 |
Due
to cost escalation |
3/06 |
8/06 |
Change
in connectivity from |
42.85 |
1.26 |
----- |
----- |
----- |
PFC- |
|
| |
Larji to Kangoo. |
|
|
of material
& labour. |
|
|
Hamirpur to Kangoo and late |
|
|
|
|
|
SP- |
|
| |
|
|
|
|
|
|
delivery of material. Line |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
commissioned
during 8/06. |
|
|
|
|
|
|
|
| B |
Deposit with HPJVNL |
|
|
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Uhal Stage - iii |
5.20 |
14.04 |
Original
scheme |
3/05 |
6/08 |
Scheme
cleared by CEA |
14.31 |
12.13 |
----- |
----- |
----- |
PFC- |
|
| |
|
|
1st revision |
sanctioned during |
|
|
during 9/02 and scheme |
|
|
|
|
|
SP- |
|
| |
|
|
32.23 |
2/91 & later on |
|
|
undertaking for preliminary |
|
|
|
|
|
|
|
| |
|
|
2nd revision |
cleared by CEA |
|
|
activities
during 2002-03. |
|
|
|
|
|
|
|
| |
|
|
|
during 9/02. |
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 2 |
220 kV Trans. Line |
23.94 |
----- |
----- |
3/05 |
7/07 |
Work
awarded on turn-key |
48.52 |
42.70 |
----- |
----- |
----- |
PFC component
|
|
| |
Kashang
to Bhaba. |
PFC |
|
|
|
|
basis during
6/05 |
|
|
|
|
|
being
revised by |
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
MD, HPJVNL. |
|
| C |
Survey & Investigation. |
|
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Detailed survey of 220kV line |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
from |
|
|
|
|
|
|
|
|
|
|
|
|
|
| I) |
Kuther to Chamera-III. |
----- |
----- |
----- |
3/07 |
----- |
----- |
0.35 |
0.30 |
----- |
----- |
----- |
S&I (SP) |
|
| ii) |
Survey of 220kV D/C line from |
----- |
----- |
----- |
3/07 |
----- |
----- |
0.30 |
0.11 |
----- |
----- |
----- |
-do- |
|
| |
Swara Kuddu to Moginand. |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 2 |
Survey of 220kV T/L from Tidong |
----- |
----- |
----- |
3/07 |
----- |
----- |
0.23 |
0.23 |
----- |
----- |
----- |
-do- |
|
| |
HEP
to Kotla and Kotla to |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Kunihar. |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 3 |
Survey of 220kV T/L from Sainj |
----- |
----- |
----- |
3/07 |
----- |
----- |
0.61 |
0.61 |
----- |
----- |
----- |
-do- |
|
| |
to Kangoo. |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contd/-2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
-2- |
|
| Sr. |
Name of Project/ |
Project Cost |
Reason
|
Projected Schedule |
Reasons |
Expdt.
|
Expdt.
|
Interest |
Deductions/ |
Transfer |
Source
|
|
| No. |
Scheme. |
Original
estimate |
Revised estimate |
for cost |
Original
completion date |
Revised
completion date |
for delay* |
up
to |
during
|
during
|
Transfers |
to Fixed |
of Captial |
|
| |
|
|
|
revision |
|
|
|
the end of |
the year |
Construction |
|
Assets |
Institution |
|
| |
|
|
|
|
|
|
|
preceding |
|
|
|
(Interest + |
wise
|
|
| |
|
|
|
|
|
|
|
year |
|
|
|
expenses
|
amount |
|
| |
|
|
|
|
|
|
|
|
|
|
|
capitalized) |
available |
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| D(I) |
State Plan(T&D)(Ongoing Schemes). |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Aug. of 132/33 kV, 2x9 |
1.89 |
----- |
Cost
escalation in |
3/06 |
----- |
One
bank commissioned |
2.23 |
0.58 |
----- |
----- |
----- |
SP |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
MVA
T/F to 2x16 MVA, |
|
|
material
& |
|
|
during 1/05 & 2nd T/F shifted |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
132/33
kV Sub-Station |
|
|
establishment
|
|
|
temporarily to Giri & shall
be |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
at Kangra. |
|
|
component. |
|
|
installed on it repatriation. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 2 |
Unified
load despatch |
7.89 |
21.59 |
Cost
escalation in |
Commissioned |
----- |
Petty job in progress. |
21.38 |
1.18 |
----- |
----- |
----- |
SP- |
|
| |
centre(SLDC) |
SP-359 |
SP-1209.41 |
material,
Estt. & |
8/01 |
|
|
|
|
|
|
|
WB- |
|
| |
|
WB-430 |
WB-950.00 |
labour components & |
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
non provision of IDC |
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 3 |
C/O 220kV S/C line from Dehar |
25.65 |
----- |
-do- |
Scheme |
----- |
-do- |
28.87 |
0.29 |
----- |
----- |
----- |
SP |
|
| |
P/H to Kangoo a/w 220/132/33 |
|
|
|
stands |
|
|
|
|
|
|
|
|
|
| |
kV S/Stn. at Kangoo. |
|
|
|
commissioned |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
long back. |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 4 |
R/R works under:- |
----- |
----- |
----- |
3/07 |
----- |
----- |
1.70 |
1.70 |
----- |
----- |
----- |
SP |
|
| |
TCM Circle, Hamirpur. |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
TCM Circle, Shimla. |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 5 |
Works
to be executed under |
----- |
----- |
----- |
----- |
----- |
----- |
0.67 |
0.67 |
----- |
----- |
----- |
SP |
|
| |
SP(T&D) 33kV & below under |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
TCM Circle, Hamirpur. |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 6 |
Prov.
Addl.16 MVA, |
1.50 |
2.63 |
-do- |
3/01 |
4/04 |
T/F were to be spared from |
2.66 |
0.06 |
----- |
----- |
----- |
SP- |
|
| |
132/11 kV T/F at Paonta. |
SP-55 |
|
|
|
|
Solan
which were spared |
|
|
|
|
|
PFC- |
|
| |
|
PFC-95 |
|
|
|
|
late due to late receipt of T/F |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
& S/Stn. Str. Of Solan. |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 7 |
220 kV
S/C line from |
10.28 |
17.06 |
Due
to cost escalation |
11/87 |
9/89 |
T-35 falling in flood zone to |
17.06 |
----- |
----- |
----- |
----- |
SP |
|
| |
Khodri to Majri (1st Ckt.) |
(SP) |
(SP) |
of material
& labour. |
|
(Commissioned) |
be shifted. Pending due to |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
abonding
of work by two |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
contractor. |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 8 |
220kV
S/C Trans. Line from |
10.24 |
----- |
Due
to cost escalation |
11/2000 |
Commissioned |
----- |
16.61 |
16.07 |
----- |
----- |
----- |
SP |
|
| |
Thein to Jassure a/w terminal |
SP-4.54 |
|
of materials & labour. |
|
during 3/01 |
|
|
|
|
|
|
|
|
| |
bay at Jassure. |
PFC-5.70 |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 9 |
220kV
S/C line from Giri to |
U/S |
----- |
----- |
3/12 |
----- |
New Scheme. |
1.20 |
1.20 |
----- |
----- |
----- |
-do- |
|
| |
Moginand
to be charged at |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
132kV a/w 220/132kV, 2x80 |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
MVA T/F at Moginand. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contd/-3 |
|
|
|
|
|
|
-3- |
|
| Sr. |
Name of Project/ |
Project Cost |
Reason
|
Projected Schedule |
Reasons |
Expdt.
|
Expdt.
|
Interest |
Deductions/ |
Transfer |
Source
|
|
| No. |
Scheme. |
Original
estimate |
Revised estimate |
for cost |
Original
completion date |
Revised
completion date |
for delay* |
up
to |
during
|
during
|
Transfers |
to Fixed |
of Captial |
|
| |
|
|
|
revision |
|
|
|
the end of |
the year |
Construction |
|
Assets |
Institution |
|
| |
|
|
|
|
|
|
|
preceding |
|
|
|
(Interest + |
wise
|
|
| |
|
|
|
|
|
|
|
year |
|
|
|
expenses
|
amount |
|
| |
|
|
|
|
|
|
|
|
|
|
|
capitalized) |
available |
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 10 |
220 kV
S/C line from |
1.90 |
----- |
Due
to cost escalation |
11/89 |
3/07 |
Due to non-availability of budget in |
9.70 |
----- |
----- |
----- |
----- |
SP |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Khodri to Majri (2nd Ckt.) |
(SP) |
|
of material
& labour. |
|
|
SP during 1999-2000, 2000-01
& |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
2001-02 approval of Extn. in
C/R & |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|