Name of Transmission Licensee:-    Transmission Wing.
Project-wise / Scheme-wise Capital Expenditure (New Projects & CWIP) FOR THE YEAR 2007-08 (PROJECTED) Form No: F15
(Rs. In Crores).
Sr. Name of Project/ Project Cost Reason Projected Schedule Reasons Expdt. Expdt. Interest Deductions/ Transfer Source
No. Scheme. Original estimate Revised estimate for cost Original completion date Revised completion date  for delay* up to during during Transfers  to Fixed of Captial
        revision       the end of the year Construction   Assets Institution
                preceding       (Interest + wise
                 year       expenses amount
                        capitalized) available
                           
1 Prov. Terminal equipment 0.39 ----- Addl. 2 Nos. 33kV bays 3/06 8/06 2 Nos. 33kV bay at Shahpur 1.27 0.34 ----- ----- ----- Gen.
  at 33/11kV S/Stn. at     being created at Shahpur     completed & 2 No. one each            
  Shapur & Kangra against Khauli      & Kangra.     at Shahpur & Kangra under            
  H.E.P.           progress.            
                           
2 C/O 132 kV D/C T/L line from 16.04 32.61 Due to cost escalation  3/06 8/06 Change in connectivity from 46.84 3.99 ----- ----- ----- PFC-
  Larji to Kangoo.     of material & labour.     Hamirpur to Kangoo and late           SP-
              delivery of material. Line            
              commissioned during 8/06.            
                           
3 Uhal Stage - iii 5.20 14.04 Original scheme 8/06 8/08 Scheme cleared by CEA 18.71 4.40 ----- ----- ----- PFC-9.91
      Revised sanctioned during     during 9/02 and scheme           SP-4.13
      again 2/91 & later on     undertaking for preliminary           Total-14.04
      submitted cleared by CEA     activities during 2002-03.            
      for Rs.3223 during 9/02.                  
      lacs.                    
                           
4 220kV line from Swara Kuddu U/S ----- Scheme cost is likely 3/10 ---- ----- 51.38 51.30 ----- ----- ----- Financial tie
  HEP to Moginand.     to be executed to                 up yet to be
        Rs.3223.00 lacs                 decided.
        based on May, 2006                  
        price level, due to cost                  
        excalation till its                  
        completion.                  
                           
5 220 kV Trans. Line 23.95 ----- Scheme completion 3/05 7/07 Work awarded on turn-key 67.90 19.38 ----- ----- ----- PFC-10.11
  Kashang to Bhaba. PFC   cost is likely to exceed     basis during 6/05           SP-13.84
        due to higher cost of                 Total-23.95
   
  material &                 PFC component
      construction head.                 being revised by
                          M.D, HPJVVNL
6 Aug. of 132/11kV, 16 MVA to U/S ----- ----- 3/08 ----- New scheme. 4.50 4.50 ----- ----- ----- Financial tie
  25/31.5 MVA T/F at Paonta.                       up yet to be
                          decided.
                           
Contd/-2
-2-
Sr. Name of Project/ Project Cost Reason Projected Schedule Reasons Expdt. Expdt. Interest Deductions/ Transfer Source
No. Scheme. Original estimate Revised estimate for cost Original completion date Revised completion date  for delay* up to during during Transfers  to Fixed of Captial
        revision       the end of the year Construction   Assets Institution
                preceding       (Interest + wise
                 year       expenses amount
                        capitalized) available
                           
7 Aug. of 132/33kV, 16 MVA T/F U/S ----- ----- 3/08 ----- New scheme. 4.00 4.00 ----- ----- ----- -do-
  at Una.                        
                           
8 220 kV S/C line from 10.29 17.06 Due to cost escalation  11/87 9/89 T-35 falling in flood zone to 17.98 0.92 ----- ----- ----- SP
  Khodri to Majri (1st Ckt.) (SP) (SP) of material & labour.     be shifted. Pending due to            
              abonding of work by two            
              contractor.            
                           
9 220 kV S/C line from 1.90 ----- Due to cost escalation  11/89 3/07 Due to non-availability of 10.08 0.38 ----- ----- ----- SP                                                  
  Khodri to Majri (2nd Ckt.) (SP)   of material & labour.     budget in SP during                                                              
              1999-2000, 2000-01 &                                                              
              2001-02 approval of                                                              
              extension in control room &                                                              
              yard not granted by                                                              
              Uttranchal utility yet.                                                              
                           
10 Unified load despatch 7.89 21.59 Cost escalation in Commissioned ----- Petty job in progress. 21.54 0.16 ----- ----- ----- SP-
  centre(SLDC) SP-359 SP-1209.41 material, Estt. & 8/01               WB-
    WB-430 WB-950.00 labour components &                  
        non provision of IDC                  
                           
11 C/O 220kV S/C line from Dehar 25.65 ----- -do- Scheme ----- -do- 29.13 0.26 ----- ----- ----- SP
  P/H to Kangoo a/w 220/132/33       stands                
  kV S/Stn. at Kangoo.       commissioned                
           long back.                
                           
12 220kV S/C Trans. Line from 10.24 ----- Due to cost escalation  11/2000 Commissioned ----- 16.69 0.08 ----- ----- ----- SP
  Thein to Jassure a/w terminal SP-4.54   of materials & labour.   during 3/01              
  bay at Jassure. PFC-5.70                      
                           
13 R/R works under:- ----- ----- ----- 3/07 ----- ----- 4.08 4.08 ----- ----- ----- SP
  TCM Circle, Hamirpur.                        
  TCM Circle, Shimla.                        
  (Works on annual basis)                        
                           
14 Works to be executed under ----- ----- ----- ----- ----- ----- 0.48 0.48 ----- ----- ----- SP
  SP(T&D) 33kV & below under                        
  TCM Circle, Hamirpur.                        
  (Works on annual basis)                        
                           
Contd/-3
-3-
Sr. Name of Project/ Project Cost Reason Projected Schedule Reasons Expdt. Expdt. Interest Deductions/ Transfer Source
No. Scheme. Original estimate Revised estimate for cost Original completion date Revised completion date  for delay* up to during during Transfers  to Fixed of Captial
        revision       the end of the year Construction   Assets Institution
                preceding       (Interest + wise
                 year       expenses amount
                        capitalized) available
                           
15 Prov. 1 No. 132/33kV, 1x16 13.89 ----- ----- 3/07 ----- ----- 14.07 6.77 ----- ----- ----- REC
  MVA & 132/11kV, 1x16 MVA                        
  S/Stn. at Gagret a/w 132/33kV                        
  S/C T/L from Amb to Gagret.                        
                           
16 220kV line from PGCIL S/Stn. 1.01 ----- ----- 3/12 ----- New scheme. 12.77 11.40 ----- ----- ----- Financial tie
  Reeru Majra to HPSEB S/Stn. submitted                   &n