|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Name
of Transmission Licensee:-
Transmission Wing. |
|
|
|
|
| Project-wise
/ Scheme-wise Capital Expenditure (New Projects & CWIP) |
|
|
FOR THE YEAR 2007-08 |
|
(PROJECTED) |
|
Form No: F15 |
|
|
|
|
|
|
(Rs. In Crores). |
|
| Sr. |
Name of Project/ |
Project Cost |
Reason
|
Projected Schedule |
Reasons |
Expdt.
|
Expdt.
|
Interest |
Deductions/ |
Transfer |
Source
|
|
| No. |
Scheme. |
Original
estimate |
Revised estimate |
for cost |
Original
completion date |
Revised
completion date |
for delay* |
up
to |
during
|
during
|
Transfers |
to Fixed |
of Captial |
|
| |
|
|
|
revision |
|
|
|
the end of |
the year |
Construction |
|
Assets |
Institution |
|
| |
|
|
|
|
|
|
|
preceding |
|
|
|
(Interest + |
wise
|
|
| |
|
|
|
|
|
|
|
year |
|
|
|
expenses
|
amount |
|
| |
|
|
|
|
|
|
|
|
|
|
|
capitalized) |
available |
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 1 |
Prov. Terminal equipment |
0.39 |
----- |
Addl.
2 Nos. 33kV bays |
3/06 |
8/06 |
2
Nos. 33kV bay at Shahpur |
1.27 |
0.34 |
----- |
----- |
----- |
Gen. |
|
| |
at
33/11kV S/Stn. at |
|
|
being
created at Shahpur |
|
|
completed
& 2 No. one each |
|
|
|
|
|
|
|
| |
Shapur & Kangra against
Khauli |
|
|
& Kangra. |
|
|
at
Shahpur & Kangra under |
|
|
|
|
|
|
|
| |
H.E.P. |
|
|
|
|
|
progress. |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 2 |
C/O
132 kV D/C T/L line from |
16.04 |
32.61 |
Due
to cost escalation |
3/06 |
8/06 |
Change
in connectivity from |
46.84 |
3.99 |
----- |
----- |
----- |
PFC- |
|
| |
Larji to Kangoo. |
|
|
of material
& labour. |
|
|
Hamirpur to Kangoo and late |
|
|
|
|
|
SP- |
|
| |
|
|
|
|
|
|
delivery of material. Line |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
commissioned
during 8/06. |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 3 |
Uhal Stage - iii |
5.20 |
14.04 |
Original
scheme |
8/06 |
8/08 |
Scheme
cleared by CEA |
18.71 |
4.40 |
----- |
----- |
----- |
PFC-9.91 |
|
| |
|
|
Revised |
sanctioned during |
|
|
during 9/02 and scheme |
|
|
|
|
|
SP-4.13 |
|
| |
|
|
again
|
2/91 & later on |
|
|
undertaking for preliminary |
|
|
|
|
|
Total-14.04 |
|
| |
|
|
submitted |
cleared by CEA |
|
|
activities
during 2002-03. |
|
|
|
|
|
|
|
| |
|
|
for Rs.3223 |
during 9/02. |
|
|
|
|
|
|
|
|
|
|
| |
|
|
lacs. |
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 4 |
220kV line from Swara Kuddu |
U/S |
----- |
Scheme cost is likely |
3/10 |
---- |
----- |
51.38 |
51.30 |
----- |
----- |
----- |
Financial tie
|
|
| |
HEP to Moginand. |
|
|
to be executed to |
|
|
|
|
|
|
|
|
up yet to be |
|
| |
|
|
|
Rs.3223.00 lacs |
|
|
|
|
|
|
|
|
decided. |
|
| |
|
|
|
based on May, 2006 |
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
price level, due to cost |
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
excalation till its |
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
completion. |
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 5 |
220 kV Trans. Line |
23.95 |
----- |
Scheme
completion |
3/05 |
7/07 |
Work
awarded on turn-key |
67.90 |
19.38 |
----- |
----- |
----- |
PFC-10.11 |
|
| |
Kashang
to Bhaba. |
PFC |
|
cost is likely to exceed |
|
|
basis during
6/05 |
|
|
|
|
|
SP-13.84 |
|
| |
|
|
|
due to higher cost of |
|
|
|
|
|
|
|
|
Total-23.95 |
|
| |
|
|
|
material
& |
|
|
|
|
|
|
|
|
PFC component
|
|
| |
|
|
construction head. |
|
|
|
|
|
|
|
|
being
revised by |
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
M.D, HPJVVNL |
|
| 6 |
Aug.
of 132/11kV, 16 MVA to |
U/S |
----- |
----- |
3/08 |
----- |
New scheme. |
4.50 |
4.50 |
----- |
----- |
----- |
Financial tie
|
|
| |
25/31.5 MVA T/F at Paonta. |
|
|
|
|
|
|
|
|
|
|
|
up yet to be |
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
decided. |
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contd/-2 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
-2- |
|
| Sr. |
Name of Project/ |
Project Cost |
Reason
|
Projected Schedule |
Reasons |
Expdt.
|
Expdt.
|
Interest |
Deductions/ |
Transfer |
Source
|
|
| No. |
Scheme. |
Original
estimate |
Revised estimate |
for cost |
Original
completion date |
Revised
completion date |
for delay* |
up
to |
during
|
during
|
Transfers |
to Fixed |
of Captial |
|
| |
|
|
|
revision |
|
|
|
the end of |
the year |
Construction |
|
Assets |
Institution |
|
| |
|
|
|
|
|
|
|
preceding |
|
|
|
(Interest + |
wise
|
|
| |
|
|
|
|
|
|
|
year |
|
|
|
expenses
|
amount |
|
| |
|
|
|
|
|
|
|
|
|
|
|
capitalized) |
available |
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 7 |
Aug.
of 132/33kV, 16 MVA T/F |
U/S |
----- |
----- |
3/08 |
----- |
New scheme. |
4.00 |
4.00 |
----- |
----- |
----- |
-do- |
|
| |
at Una. |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 8 |
220 kV
S/C line from |
10.29 |
17.06 |
Due
to cost escalation |
11/87 |
9/89 |
T-35 falling in flood zone to |
17.98 |
0.92 |
----- |
----- |
----- |
SP |
|
| |
Khodri to Majri (1st Ckt.) |
(SP) |
(SP) |
of material
& labour. |
|
|
be shifted. Pending due to |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
abonding
of work by two |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
contractor. |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 9 |
220 kV
S/C line from |
1.90 |
----- |
Due
to cost escalation |
11/89 |
3/07 |
Due
to non-availability of |
10.08 |
0.38 |
----- |
----- |
----- |
SP |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
Khodri to Majri (2nd Ckt.) |
(SP) |
|
of material
& labour. |
|
|
budget
in SP during |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
1999-2000,
2000-01 & |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
2001-02
approval of |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
extension
in control room & |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
yard
not granted by |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
Uttranchal utility yet. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 10 |
Unified
load despatch |
7.89 |
21.59 |
Cost
escalation in |
Commissioned |
----- |
Petty job in progress. |
21.54 |
0.16 |
----- |
----- |
----- |
SP- |
|
| |
centre(SLDC) |
SP-359 |
SP-1209.41 |
material,
Estt. & |
8/01 |
|
|
|
|
|
|
|
WB- |
|
| |
|
WB-430 |
WB-950.00 |
labour components & |
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
non provision of IDC |
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 11 |
C/O 220kV S/C line from Dehar |
25.65 |
----- |
-do- |
Scheme |
----- |
-do- |
29.13 |
0.26 |
----- |
----- |
----- |
SP |
|
| |
P/H to Kangoo a/w 220/132/33 |
|
|
|
stands |
|
|
|
|
|
|
|
|
|
| |
kV S/Stn. at Kangoo. |
|
|
|
commissioned |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
long back. |
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 12 |
220kV
S/C Trans. Line from |
10.24 |
----- |
Due
to cost escalation |
11/2000 |
Commissioned |
----- |
16.69 |
0.08 |
----- |
----- |
----- |
SP |
|
| |
Thein to Jassure a/w terminal |
SP-4.54 |
|
of materials & labour. |
|
during 3/01 |
|
|
|
|
|
|
|
|
| |
bay at Jassure. |
PFC-5.70 |
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 13 |
R/R works under:- |
----- |
----- |
----- |
3/07 |
----- |
----- |
4.08 |
4.08 |
----- |
----- |
----- |
SP |
|
| |
TCM Circle, Hamirpur. |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
TCM Circle, Shimla. |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
(Works on annual basis) |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 14 |
Works
to be executed under |
----- |
----- |
----- |
----- |
----- |
----- |
0.48 |
0.48 |
----- |
----- |
----- |
SP |
|
| |
SP(T&D) 33kV & below under |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
TCM Circle, Hamirpur. |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
(Works on annual basis) |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contd/-3 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
-3- |
|
| Sr. |
Name of Project/ |
Project Cost |
Reason
|
Projected Schedule |
Reasons |
Expdt.
|
Expdt.
|
Interest |
Deductions/ |
Transfer |
Source
|
|
| No. |
Scheme. |
Original
estimate |
Revised estimate |
for cost |
Original
completion date |
Revised
completion date |
for delay* |
up
to |
during
|
during
|
Transfers |
to Fixed |
of Captial |
|
| |
|
|
|
revision |
|
|
|
the end of |
the year |
Construction |
|
Assets |
Institution |
|
| |
|
|
|
|
|
|
|
preceding |
|
|
|
(Interest + |
wise
|
|
| |
|
|
|
|
|
|
|
year |
|
|
|
expenses
|
amount |
|
| |
|
|
|
|
|
|
|
|
|
|
|
capitalized) |
available |
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 15 |
Prov.
1 No. 132/33kV, 1x16 |
13.89 |
----- |
----- |
3/07 |
----- |
----- |
14.07 |
6.77 |
----- |
----- |
----- |
REC |
|
| |
MVA & 132/11kV, 1x16 MVA |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
S/Stn. at Gagret a/w 132/33kV |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
S/C T/L from Amb to Gagret. |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 16 |
220kV
line from PGCIL S/Stn. |
1.01 |
----- |
----- |
3/12 |
----- |
New scheme. |
12.77 |
11.40 |
----- |
----- |
----- |
Financial tie
|
|
| |
Reeru
Majra to HPSEB S/Stn. |
submitted |
|
|
|
|
|
|
|
|
|
&n |