| Name of Transmission Licensee:HPSEB | |||||||||
| Peak Demand in MW | Form No: P9 | ||||||||
| Sr. | Actual | Actual | Actual | Actual | Actual | Previous | Current | Ensuing | |
| No. | FY (n-5) | FY (n-4) | FY (n-3) | FY (n-2) | FY (n-1) | Year | Year | Year | |
| Provisional | Estimate | Projection | |||||||
| FY (n) | FY (n+1) | FY (n+2) | |||||||
| 2000-01 | 2001-02 | 2002-03 | 2003-04 | 2004-05 | 2005-06 | 2006-07 | |||
| 1 | Peak Period | ||||||||
| a) Winter(Dec., 2004) | Under Op. | 360.00 | 390.10 | 410.20 | 457.02 | 507.02 | 557.72 | 601.72 | |
| Wing | |||||||||
| b) Summer(June, 2004) | -do- | 435.40 | 460.40 | 499.80 | 521.80 | 575.89 | 633.46 | 683.70 | |
| c) Other(March, 2005) | -do- | 416.00 | 439.10 | 469.00 | 499.10 | 532.71 | 560.00 | 590.00 | |
| 2 | Maximum Peak Demand | Load restricted/to be restricted as per the direction of Power Controller and | |||||||
| a) Restricted | it was/is not accounted. | ||||||||
| b) Unrestricted | |||||||||
| 3 | Peak Availability Assessed | ---- | ---- | ---- | ---- | 620.00 | 700.00 | 750.00 | |
| By Transco | |||||||||
| 4 | Shortfall in meeting Peak | As per directions of Power Controller. | |||||||
| Demand | |||||||||
| a) Restricted | |||||||||
| b) Unrestricted | |||||||||
| Notes:- Details of Peak Demand and Load Rostering may be provided along with this format ie., in terms of MW, MU | |||||||||
| and number of hours per day. | |||||||||