FORM-2  
  Details of COD, Type of hydro station, Capacity Index, Primary energy rate      
NAME OF COMPANY:           HPSEB                                                             
NAME OF POWER STATION :    BANER POWER HOUSE
         
Sl. No. Description   As per CERC norms for tariff period 2004-05 to 2008-09
   
1 Installed Capacity MW 3x4MW - 12 MW
2 Free power to home state % _____
3 Date of commercial operation    
  Unit-1   13-5-96
  Unit-2   25-8-96
  Unit-3   18-5-96
4 Type of Station    
  a) Surface/underground   surface
  b) Purely ROR/ Pondage/Storage   ROR
  c) Peaking/non-peaking   Non-Peaking
  d) No. of hours of peaking   ___
  e) Overload capacity(MW) & period   Nil  
5 Type of excitation    
  a) Rotaing exciters on generator   NO
  b) Static excitation   Static
6 Design Energy (Annual)1 Gwh 57.64*
7 Auxiliary Consumption % 0.5% 0.29 GWH
8 Transformation losses % 0.5% 0.29 GWH
9 Saleable Primary Energy Gwh 42.79  
10 Primary Energy Rate paise/Kwh 152
11 Primary Energy Charge Rs. in crore  
12 Capacity Index   74.23%**
  Normative value    
  1 Monthwise Design energy figures to be given separately with the petition.      
  *(95%of 90% dependable year)      
  **Targeted energy/design energy(9/6)   PETITIONER