| |
Break up of Capital cost for hydro power generating station |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
NAME OF COMPANY: |
|
HPSEB |
|
FORM-5B, -
(P-1) Civil Works |
|
| |
NAME OF POWER
STATION:
Bassi Power House |
|
| |
|
(Rs. in
crore)
|
|
| Sl.
No. |
Head
of works |
Original cost as
approved by Authority |
Exp.
Ending 3/06 |
Cost on
COD |
Variation |
Reasons
for variation |
Admitted cost |
|
|
| 1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| 1.0 |
Infrastructure
Works |
|
|
|
|
|
|
|
| 1.1 |
Preliminary
including Development |
|
|
|
|
|
|
|
| 1.2 |
Land |
|
15.77 |
|
|
|
|
|
| 1.3 |
Buildings |
|
211.68 |
|
|
|
|
|
| 1.4 |
Township |
|
|
|
|
|
|
|
| 1.5 |
Maintenance |
|
|
|
|
|
|
|
| 1.6 |
Tools & Plants |
|
|
|
|
|
|
|
| 1.7 |
Communication |
|
10.73 |
|
|
|
|
|
| 1.8 |
Environment &
Ecology |
|
|
|
|
|
|
|
| 1.9 |
Losses on stock |
|
|
|
|
|
|
|
| 1.10 |
Receipt &
Recoveries |
|
|
|
|
|
|
|
| 1.11 |
Total
(Infrastructure works) |
|
0.00 |
|
|
|
|
|
| 2.0 |
Major Civil Works |
|
|
|
|
|
|
|
| 2.1 |
Dam, Intake & Desilting
Chambers |
|
836.80 |
|
|
|
|
|
| 2.2 |
HRT, TRT, Surge Shaft & Pressure
shafts |
|
|
|
|
|
|
|
| 2.3 |
Power Plant civil works |
|
28.40 |
|
|
|
|
|
| 2.4 |
Other civil works (to be specified) |
|
|
|
|
|
|
|
| 2.5 |
Total
(Major Civil Works) |
|
865.20 |
|
|
|
|
|
| 3.0 |
Hydro Mechanical equipments |
|
|
|
|
|
|
|
| 4.0 |
Plant & Equipment |
|
576.52 |
|
|
|
|
|
| 4.1 |
Initial spares of Plant &
Equipment |
|
186.79 |
|
|
|
|
|
| 4.2 |
Total (Plant & Equipment) |
|
763.31 |
|
|
|
|
|
| 5.0 |
Taxes and Duties |
|
|
|
|
|
|
|
| 5.1 |
Custom Duty |
|
|
|
|
|
|
|
| 5.2 |
Other taxes & Duties |
|
|
|
|
|
|
|
| 5.3 |
Total Taxes & Duties |
|
|
|
|
|
|
|
| 6.0 |
Construction & Pre-commissioning expenses |
|
|
|
|
|
|
|
| 6.1 |
Erection, testing &
commissioning |
|
|
|
|
|
|
|
| 6.2 |
Construction Insurance |
|
|
|
|
|
|
|
| 6.3 |
Site supervision |
|
|
|
|
|
|
|
| 6.4 |
Total (Const. &
Pre-commissioning) |
|
|
|
|
|
|
|
| 7.0 |
Overheads |
|
|
|
|
|
|
|
| 7.1 |
Establishment |
|
|
|
|
|
|
|
| 7.2 |
Design & Engineering |
|
|
|
|
|
|
|
| 7.3 |
Audit
& Accounts |
|
|
|
|
|
|
|
| 7.4 |
Contingency |
|
|
|
|
|
|
|
| 7.5 |
Rehabilitation
& Resettlement |
|
|
|
|
|
|
|
| 7.6 |
Total
(Overheads) |
|
|
|
|
|
|
|
| 8.0 |
Capital
Cost without IDC & FC |
|
1628.51 |
|
|
|
|
|
| 9.0 |
Financing
charges (FC) |
|
|
|
|
|
|
|
| 10.0 |
Interest during construction
(IDC) |
|
311.93 |
|
|
|
|
|
| 11.0 |
Capital
Cost with IDC & FC |
|
1940.44 |
|
|
|
|
|
|
Note: |
|
|
|
1. In case of time and cost over-run of the
project, a detailed note giving reasons of such time and cost over run should
be submitted, clearly |
|
|
bringing out the
agency responsible and whether such time and cost over run was beyond the
control of the generating company. |
|
|
|
|
|
|
|
PETITIONER
|
|
|
|
|
|
|
|
| |
Break
up of Capital cost for hydro power generating station |
|
| |
NAME OF COMPANY: |
|
HPSEB |
|
FORM-5B, -
(P-2) EM Works |
|
| |
NAME OF POWER
STATION:
Bassi Power House |
|
| |
|
(Rs. in
crore)
|
|
| Sl.
No. |
Head
of works |
Original cost as
approved by Authority |
Exp.
Ending 3/06 |
Cost on COD |
Variation |
Reasons
for variation |
Admitted cost |
|
|
| 1 |
2 |
3 |
4 |
5 |
|
6 |
7 |
|
| 1.0 |
Infrastructure
Works |
|
|
|
|
|
|
|
| 1.1 |
Preliminary
including Development |
|
|
|
|
|
|
|
| 1.2 |
Land |
|
15.77 |
|
|
|
|
|
| 1.3 |
Buildings |
|
216.40 |
|
|
|
|
|
| 1.4 |
Township |
|
|
|
|
|
|
|
| 1.5 |
Maintenance |
|
|
|
|
|
|
|
| 1.6 |
Tools & Plants |
|
|
|
|
|
|
|
| 1.7 |
Communication |
|
27.18 |
|
|
|
|
|
| 1.8 |
Environment &
Ecology |
|
|
|
|
|
|
|
| 1.9 |
Losses on stock |
|
|
|
|
|
|
|
| 1.10 |
Receipt &
Recoveries |
|
|
|
|
|
|
|
| 1.11 |
Total
(Infrastructure works) |
|
259.35 |
|
|
|
|
|
| 2.0 |
Major Civil Works |
|
|
|
|
|
|
|
| 2.1 |
Dam, Intake & Desilting
Chambers |
|
836.80 |
|
|
|
|
|
| 2.2 |
HRT, TRT, Surge Shaft & Pressure
shafts |
|
|
|
|
|
|
|
| 2.3 |
Power Plant civil works |
|
58.45 |
|
|
|
|
|
| 2.4 |
Other civil works (to be specified) |
|
|
|
|
|
|
|
| 2.5 |
Total
(Major Civil Works) |
|
895.25 |
|
|
|
|
|
| 3.0 |
Hydro Mechanical equipments |
|
|
|
|
|
|
|
| 4.0 |
Plant & Equipment |
|
578.42 |
|
|
|
|
|
| 4.1 |
Initial spares of Plant &
Equipment |
|
668.85 |
|
|
|
|
|
| 4.2 |
Total (Plant & Equipment) |
|
1247.27 |
|
|
|
|
|
| 5.0 |
Taxes and Duties |
|
|
|
|
|
|
|
| 5.1 |
Custom Duty |
|
|
|
|
|
|
|
| 5.2 |
Other taxes & Duties |
|
|
|
|
|
|
|
| 5.3 |
Total Taxes & Duties |
|
|
|
|
|
|
|
| 6.0 |
Construction & Pre-commissioning expenses |
|
|
|
|
|
|
|
| 6.1 |
Erection, testing &
commissioning |
|
|
|
|
|
|
|
| 6.2 |
Construction Insurance |
|
|
|
|
|
|
|
| 6.3 |
Site supervision |
|
|
|
|
|
|
|
| 6.4 |
Total (Const. &
Pre-commissioning) |
|
|
|
|
|
|
|
| 7.0 |
Overheads |
|
|
|
|
|
|
|
| 7.1 |
Establishment |
|
|
|
|
|
|
|
| 7.2 |
Design & Engineering |
|
|
|
|
|
|
|
| 7.3 |
Audit
& Accounts |
|
|
|
|
|
|
|
| 7.4 |
Contingency |
|
|
|
|
|
|
|
| 7.5 |
Rehabilitation
& Resettlement |
|
|
|
|
|
|
|
| 7.6 |
Total
(Overheads) |
|
|
|
|
|
|
|
| 8.0 |
Capital
Cost without IDC & FC |
|
2401.87 |
|
|
|
|
|
| 9.0 |
Financing
charges (FC) |
|
|
|
|
|
|
|
| 10.0 |
Interest during construction
(IDC) |
|
402.53 |
|
|
|
|
|
| 11.0 |
Capital
Cost with IDC & FC |
|
2804.40 |
|
|
|
|
|
|
Note: |
|
|
|
1. In case of time and cost over-run of the
project, a detailed note giving reasons of such time and cost over run should
be submitted, clearly |
|
|
bringing out the
agency responsible and whether such time and cost over run was beyond the
control of the generating company. |
|
|
|
|
|
|
|
PETITIONER
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|