| FORM- 6 | ||||||
| Financial Package upto COD | ||||||
| Name of the Company | HPSEB | |||||
| Name of the Power Station | Bassi Power House | |||||
| Project Cost as on COD1 | ____________________________________ | |||||
| Date of Commercial Operation of the Station2 | ____________________________________ | |||||
| (Amount in lacs) | ||||||
| Financial Package as Approved | Financial Package as on COD | As Admitted on COD | ||||
| Currency and Amount3 | Currency and Amount3 | Currency and Amount3 | ||||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| Loan-I | US $ | |||||
| Loan-II | ||||||
| Loan-III | ||||||
| and so on | ||||||
| Equity- | ||||||
| Foreign | ||||||
| Domestic | ||||||
| Total Equity | ||||||
| Debt : Equity Ratio | ||||||
| 1 Say US $ 200m + Rs.400 Cr or Rs.1200 Cr including US $200m at an exchange rate of 1US $=Rs.40/- | ||||||
| 2 Date of Commercial Operation means Commercial Operation of the last unit | ||||||
| 3 For example : US $, 200M etc.etc | ||||||
| Petitioner | ||||||