FORM- 1
Summary Sheet
Name of the Company HPSEB
Name of the Power Station : BHABA  POWER HOUSE
Region State District
HIMACHAL SHIMLA
(Rs. in lacs)
S.No. Particulars    2003-04 2004-05 2005-06 2006-07 2007-08 2008-09
1 2   3 4 5 6 7 8
                 
1 Depreciation FORM- 11            
2 Interest on Loan FORM- 13A            
3 Return on Equity1              
4 Advance against Depreciation FORM- 14            
5 Interest on Working Capital FORM- 15            
6 O & M Expenses   843.83 785.95 1105 1149 1195 1243
                 
  Total              
1 Details of calculations, considering equity as per regulation, to be furnished.