| FORM- 10 | ||||||||||||
| Financing of Additional Capitalisation | ||||||||||||
| Name of the Company | HPSEB | |||||||||||
| Name of the Power Station | GIRI POWER HOUSE | |||||||||||
| Date of Commercial Operation | 16 Th April, 1978 | |||||||||||
| (Amount in lacs) | ||||||||||||
| Actual | Admitted | |||||||||||
| Financial Year (Starting from COD) | Year1 | Year2 | Year3 | Year4 | Year 5 & So on | Year1 | Year2 | Year3 | Year4 | Year 5 & So on | ||
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | ||
| Amount capitalised in Work/Equipment | - | - | - | - | 1556.98 | - | - | - | - | 1556.98 | ||
| - | - | - | - | - | - | - | - | - | ||||
| Financing Details | - | - | - | - | - | - | - | - | - | |||
| Loan-1 PFC | - | - | - | - | 555.78 | - | - | - | - | 555.78 | ||
| Loan-2 | - | - | - | - | - | - | - | - | - | |||
| Loan-3 and so on | - | - | - | - | - | - | - | - | - | |||
| Total Loan2 | - | - | - | - | - | - | - | - | - | |||
| - | - | - | - | - | - | - | - | |||||
| Equity State Plan | - | - | - | - | 470.41 | - | - | - | - | 470.41 | ||
| Internal Resources | - | - | - | - | - | - | - | - | - | |||
| Others I.D.C. | - | - | - | - | 530.79 | - | - | - | - | 530.79 | ||
| - | - | - | - | - | - | - | - | - | - | |||
| Total | - | - | - | - | 1556.98 | - | - | - | 1556.98 | |||
| 1 Year 1 refers to Financial Year of COD and Year 2, Year 3 etc. are the subsequent financial years respectively. | ||||||||||||
| 2 Loan details for meeting the additional capitalisation requirement should be given as per FORM-7 or 8 whichever is relevent. | ||||||||||||
| Petitioner | ||||||||||||