Break up of Capital Cost for Plant & Equipment FORM 5 C
  NAME OF COMPANY: HPSEB  
  NAME OF POWER STATION:2x1.5 MW Gumma Power House.  
                                                           (Rs. in LAC)                                                                                                             
Sl. No. Head of works Original Cost as approved  by Authority     Cost on COD Variation Reasons for variation Admitted cost lacs
1 2 3 4 5 6 7
1.0 Generator, turbine & Acessories          
1.1 Generator package          
1.2 Turbine package          
1.3 Unit control Board          
1.4 C&I package          
1.5 Bus Duct of GT connection          
1.6 Total (Generator, turbine & Acessories) 300 944.66 (+)644.66 high cost 944.66
2.0 Auxiliary Electrical Equipment 6 6.47 (+) 0.47   6.47
2.1 Step up transformer 20 18.59 (-)1.41   18.59
2.2 Unit Auxiliary Transformer          
2.3 Local supply transformer          
2.4 Station transformer 15 8.57 (-) 6.43   8.57
2.5  SCADA          
2.6 Switchgear, Batteries, DC dist. Board  18.00 12.83 (-) 5.17   12.83
2.7 Telecommunication equipment          
2.8 Illumination of Dam, PH and Switchyard 5.00 5.04 (+)0.04   5.04
2.9 Cables & cable facilities, grounding          
2.10 Diesel generating sets          
2.11 Total (Auxiliary Elect. Equipment)   60.89     60.89
3.0 Auxiliary equipment & services for power station          
3.1 EOT crane 10.40 14.04 (+)3.64   14.04
3.2 Other cranes          
3.3 Electric lifts & elevators          
3.4 Cooling water system          
3.5 Drainage & dewatering system          
3.6 Fire fighting equipment 2.00 3.10 (+)1.1   3.1
3.7 Air conditioning, ventilation and heating          
3.8 Water supply system          
3.9 Oil handling equipment          
3.10 Workshop machines & equipment          
3.11 Total (Auxiliary equipt. & services for PS)           
4.0 Switchyard package   6.13     6.13
5.0 Initial spares for all above equipments         1080.32
6.0 Total (Plant & Equipment)         lacs
   
PETITIONER