FORM-9
                Statement of Additional Capitalisation after COD
Name of the Company : HPSEB
Name of Power Station:  2x1.25 MW Ghanvi  Power House.
COD : 9/20/1987
Sl.No Year Work/Equipment Amount Capitalised/ Justification Admitted
    added after COD Proposed to be   CostI
    up to Cut off Date/ Capitalised    
    Beyond Cut off        
    Date          
1 2 3 4 5 6
               
               
               
               
               
               
               
               
               
               
               
               
           
           
           
           
  Total   54.00   54.00
1 In case of the project has been completed and any tariff notification(s) has already been issued in
the past by Govt. of India, fill column 6 giving the cost as admitted for the purpose of tariff notification
already issued by (Name of the authority) (Enclose copy of the tariff Order)
Note:
1. Fill the form in chronological order year wise along with detailed justificatgion clearly bringing out 
the necessity and the benefits accruing to the beneficiaries.
2. In case initial spares are purcahsed alongwith any equipment , then the cost of such spares should
be indicated separately,e.g. Rotor- 50 Crs. Initial spares - 5 Crs.
PETITIONER