FORM-5A  
Abstract of  Capital Cost Estimates and Schedule of Commissioning for the New projects
   
Name of the Company : Himachal Pradesh State Electricity Board  
   
Name of the Power Station : Khauli HEP  
 
 
New Projects C-Civil works 3903.00 Lacs  
Capital Cost Estimates Rs. 8987.00 Lacs E-Elect. Works 2176.00 lacs  
  T-Transmission 529.00 lacs  
Board of Director/ Agency approving the project cost estimates: CEA & HPSEB          
               
Date of approval of the Capital cost estimates: Apr-96            
  Present Day Cost  Completed Cost  
Price level of approved estimates As of End of __2nd_Qtr. Of the year _1996_ As on Scheduled COD of the Station  
               
Foreign Exchange rate considered for the capital cost estimates              
               
Capital Cost excluding IDC & FC              
               
Foreign Component, if any (In Million US $ or the relevant Currency)              
               
Domestic Component (Rs. Cr.)              
               
Capital cost excluding IDC & FC (Rs. Cr)              
               
IDC & FC 2098.00            
               
Foreign Component, if any (In Million US $ or the relevant Currency) 313500 Swiss France (1114 lacs)        
               
Domestic Component (Rs. Cr.) 7873.00            
               
IDC & FC (Rs.Cr.)              
               
Rate of taxes & duties considered              
               
Schedule of Commissioning              
               
COD of Unit-I Nov. 2006          
               
COD of Unit-II Dec. 2006          
               
               
COD of last Unit --            
               
Note:    
1. Copy of approval letter should be enclosed.  
2. Details of capital cost are to be furnished as per FORM-5B or 5C as applicable.  
3. Details of IDC & Financing Charges are to be furnished as per FORM-16.  
   
   