FORM-5A  
Abstract of  Capital Cost Estimates and Schedule of Commissioning for the New projects
   
Name of the Company : HPSEB  
   
Name of the Power Station : 3x42 MW Larji  Power House. Dawada  
   
New Projects yes New  
Capital Cost Estimates Rs 213.67 crores with T& C  
   
Board of Director/ Agency approving the project cost estimates: CEA New Delhi          
               
Date of approval of the Capital cost estimates: April,2004          
  Present Day Cost  Completed Cost  
Price level of approved estimates As of End of ______Qtr. Of the year _________ As on Scheduled COD of the Station  
        Rs.232.60crores Appx.  
Foreign Exchange rate considered for the capital cost estimates   Rs.47/dollar        
               
Capital Cost excluding IDC & FC              
               
Foreign Component, if any (In Million US $ or the relevant Currency) 5200000 US Dollars        
               
Domestic Component (Rs. Cr.) Rs.5247000 only          
               
Capital cost excluding IDC & FC (Rs. Cr) Rs. 232.60 crores of Elect. Component        
               
IDC & FC Rs.60.32 crores          
               
Foreign Component, if any (In Million US $ or the relevant Currency)              
               
Domestic Component (Rs. Cr.)              
               
IDC & FC (Rs.Cr.)              
               
Rate of taxes & duties considered ED 16.02% & CST @4% on C form        
               
Schedule of Commissioning              
               
COD of Unit-I 15th December,2006 Last unit      
               
COD of Unit-II 12.10.06          
               
-------------------------              
               
---------------------------              
               
COD of last Unit 26.09.06 unit III          
               
Note:    
1. Copy of approval letter should be enclosed.  
2. Details of capital cost are to be furnished as per FORM-5B or 5C as applicable.  
3. Details of IDC & Financing Charges are to be furnished as per FORM-16.  
   
   