FORM- 5C
                                        Break up of Capital Cost for Plant & Equipment  
   
  NAME OF COMPANY: Himachal Pradesh State Electricity Board
  NAME OF POWER STATION:                          3 x 42 MW Larji Hydel Project  
                                                           (Rs. in crore)                                                                                                             
Sl. No. Head of works Original Cost as approved  by Authority
in lacs.    
Cost on COD Variation Reasons for variation Admitted cost
1 2 3 4 5 6 7
1.0 Generator, turbine & Acessories          
1.1 Generator package 8615.54 8215.54      
1.2 Turbine package        
1.3 Unit control Board 199.15 125      
1.4 C&I package          
1.5 Bus Duct of GT connection 232.00 144      
  Miscellaneous 163.88 75.6      
1.6 Total (Generator, turbine & Acessories) 9210.57 8560.14      
2.0 Auxiliary Electrical Equipment          
2.1 Step up transformer 382.80 355      
2.2 Unit Auxiliary Transformer 15.66        
2.3 Local supply transformer 18.56        
2.4 Station transformer 34.80        
2.5  SCADA 430.16 676     due torise
2.6 L.T. Switchgear 69.60       in rates
 Batteries, 34.80 77.00   42.2 due torise
DC dist. Board  5.80       in rates
11 kV Distribution Board 15.66        
2.7 Telecommunication equipment 22.04        
2.8 Illumination of Dam, PH and Switchyard 87.00 20.00      
2.9 Cables 469.80 254.23      
Cable facilities, 55.68        
Grounding 92.80 80.00      
2.10 Diesel generating sets 23.20 20.00      
  Miscellaneous 34.63        
  Electrical Test & Lab. Equip. 46.40        
  Transformer rails 4.64      
2.11 Total (Auxiliary Elect. Equipment) 1844.03 1482.23      
3.0 Auxiliary equipment & services for power station          
3.1 EOT crane        
  125/25 T 139.20 82.00      
  5 T 11.60 5.00      
3.2 Other cranes 42.63        
3.3 Electric lifts & elevators 27.84 7.00      
3.4 Cooling water system 162.40 45.65      
3.5 Drainage & dewatering system 46.40 33.00      
3.6 Fire fighting equipment 87.00 20.00      
3.7 Air conditioning, ventilation and heating 84.50 77.00      
3.8 Water supply system 17.40 5.00      
3.9 Oil handling equipment 17.40 10.00      
3.10 Workshop machines & equipment 34.80 10.00      
  Assembly line facilities i/c hard standing 11.60        
  Miscellaneous 11.82        
  Hatchways 11.60 5.00      
3.11 Total (Auxiliary equipt. & services for PS) 706.19 299.65      
4.0 Switchyard package 2060.56 173.00      
5.0 Initial spares for all above equipments          
  Spares for Generator, turbine & accessories 633.94 255.00      
  Spares for auxiliary electrical equip. 51.66 10.50      
  Spares for auxiliary equip. & services 20.96        
  Spares for switchyard 56.71 48.70      
  Total spares 763.27 314.20      
6.0 Total (Plant & Equipment) 14584.62        
             
1 Preliminary works 295.90        
2 Total (Generator, turbine & Acessories) 9210.57        
Total (Auxiliary Elect. Equipment) 1844.03        
Total (Auxiliary equipt. & services for PS) 706.19        
Spares for above 706.56        
Sub total 12467.35        
  CST on the above 498.69 5.6      
  Transportation, handling & insurance charges @ 6% 748.04 650      
  Erection & commissioning charges @ 8% 997.39 850      
  Total generating plant & equip. 14711.47 1505.6      
             
3 Switchyard package 2060.56 900      
Spares for above 56.71        
Sub total 2117.27        
  CST on the above 84.69 36      
  Transportation, handling & insurance charges @ 6% 127.04 60      
  Erection & commissioning charges @ 8% 169.38 72      
  Total for swithchyard package 2498.38 168      
4 Losses on stock @ .25% 40.11        
5 Maintenance during construction @ 1.00% 160.43 15      
6 Procurement & inspection charges @ 2% 320.86 54      
7 Contigency @ 3% in items 2 & 3 516.30 315      
8 Total 18543.45        
9 Establishment @ 6% of above. 1112.61 820      
10 T&P @ 1% 185.43 38      
11 Audit & accounts charges @ 1% 185.43 19      
  Grand total 20026.92        
             
Note: - There is a totalling error of Rs.52.80 lacs in the in auxiliary equipment sub total which is given as Rs.2042.04 in the DPR whereas it should be Rs.2094.84lacs.
             