Basinwise Potential in H.P.
SATLUJ  BASIN

S.No. Name River/Khad MW
1 Rongtong On Rongtong Khad 2
2 Rukti Rukti Khad 1.5
3 SVP Bhaba On Bhaba Khad 120
4 Ghanvi On Ghanvi Khad 22.5
5 Nogli Stage-I On Nogli 2.5
6 Chaba On Nauti Khad 1.75
7 Bhakra Dam On Satluj 1200
8 Bhaba Aug. P/H On Shango Khad 4.50
9 Keshang-I On Keshang Khad 66
10 Ghanvi-II On Ghanvi Khad 10
11 Yangthang Khab On Spiti 400
12 Khab -I On Satluj 450
13 Khab -II On Satluj 186
14 Thopan Powari On Satluj 400
15 Baspa Stage-I Baspa 210
16 Sorang On Satluj 60
17 Tidong-I On Satluj 100
18 Tidong-II On Satluj 90
19 Bahairari Bahajrari Khad 5.5
20 Kashang-II On Keshang Khad 60
21 Kashang-III On Keshang Khad 132
22 Luri Satluj 425
23 Jhangi Thopan On Satluj 480
24 Kuling Lara On Spiti 40
25 Lara Project On Spiti 60
26 Mani Nadang On Spiti 70
27 Lara Sumata On Spiti 104
28 Sumta-Kathang Kothans 130
29 Chango Yangthang On Spiti 140
30 Ropa Tidong Khad 60
31 Baspa Stage-II On Baspa 300
32 Karcham Wangtoo Satluj 1000
33 Nathpa Jhakri On Baspa 1500
34 Kol Dam On Satluj 800
35 Rampur On Satluj 400
36 Shongtong-Karcham On Satluj 402
37 Kut 15
  Total   9420.25
I. Under Operation. 3150.25
II. Under Construction with State Sector. 80.50
III. Under Private/Joint Sector/Central Sector 1200.00
IV.Under Investigation. 832.00
V. DPR Ready 1402.00
VI Projects Identified 2755.50
Total   9420.25

 


Beas Basin   |  Yamuna Basin  |  Satluj Basin  |  Ravi Basin   |  Chenab Basin

back.gif (7582 bytes)


History   |  Organization  |  Achievements & Milestones  |  Hydro Potential
Invest in Hydro  |  Mission  | Our Commitment  |   Hydro Policy   |  Tenders  |  Feedback  |  Contact  |   HOME