1. THE COST DATA FOR
DISTRIBUTION SUB-STATION EQUIPMENTS AND MATERIAL FOR LINES INDICATES THE RATES
FOR INDIVIDUAL ITEMS. THE COMPLETE ESTIMATE FOR A WORK SHALL HOWEVER
BE PREPARED ON THE BASIS OF ACTUAL LAY OUT OF THE DISTRIBUTION SUB-STATION
& OTHER REQUIREMENTS ETC.
2. COST OF CIVIL WORKS
FOR LINES, DISTRIBUTION SUB-STATION AND EQUIPMENT HAS NOT BEEN INCORPORATED
WHICH OTHER WISE VARIES FROM PLACE TO PLACE. THE AREA & SITE SPECIFIC CONDITIONS
SHALL BE TAKEN INTO ACCOUNT WHILE PREPARING THE ESTIMATES.
3. COST OF LAND FOR
DISTRIBUTION SUB-STATION AND LINES WHICH COMPRISES OF REQUIREMENT OF LAND
EXCAVATION IS NOT ENVISAGED IN THE COST DATA AND WILL BE INCORPORATED IN THE
ESTIMATES AS PER ACTUAL REQUIREMENTS.
4. ESCALATION IN RESPECT
OF THE PERIOD OF IMPLEMENTATION BEYOND 31.03.10 SHALL BE CHARGED @ 10% PER ANNUM
WITH (WITH ANNUAL COMPOUNDING) OVER AND ABOVE THE RATES INDICATED IN THIS COST
DATA. THE ESCALATION SHALL BE CHARGED FROM 1.4.2010 TO THE DATE OF COMMISSIONING
OF THE WORKS. ESCALATION FOR PART OF YEAR SHALL BE WORKED OUT ON PROPORATA
BASIS IN PROPORTION TO THE NUMBER OF MONTHS.
5. THE RATES OF COST DATA FOR 2009-10 HAVE BEEN
ESTIMATED BY TAKING INTO ACCOUNT COST ESCALATION @ 10% OVER THE CALCULATED
COST IN THE COST DATA FOR THE YEAR 2008-09 IN RESPECT OF ITEMS P.O. FOR WHICH
HAS NOT BEEN PLACED DURING THE INTERVENING PERIOD AND IN RESPECT OF ITEMS
P.O. FOR WHICH HAS BEEN PLACED DURING 2008, HPSEB MAY HOWEVER REVISE THE COST
DATA AND THE RELEVANT ESTIMATES AT ANY TIME BASED ON THE ACTUAL
PROCUREMENT PRICES IN CASE OF ABNORMAL DEVIATIONS FOR ANY ITEM(S)
6. THE ESTIMATES FOR THE WORKS/EQUIPMENTS NOT
SPECIFICALLY COVERED IN THE COST DATA SHALL BE PREPARED BY SUITABLY TAKING INTO
ACCOUNT THE ESTIMATED COST OF THE OTHER SIMILAR EQUIPMENTS/ WORKS
INCLUDED IN THE COST DATA ALONGWITH SUITABLE MODIFICATIONS AND THE EFFECT OF
OTHER RELEVANT FACTORS SPECIFIC TO THE WORKS/ EQUIPMENT TO BE ESTIMATED.
7. IN CASE OF WORKS
AWARED ON TURN-KEY BASIS AFTER FOLLOWING THE BIDDING PROCESS. THE ESTIMATES
SHALL BE PREPARED/ REVISED ON THE BASIS OF COST AS PER SUCH AWARDS
8.
THE PRICES ARE SUBJECT TO INCREASE OR DECREASE AS PER IEEMA FORMULA APPLICABLE
FOR THE BASIC RAW MATERIAL i.e. STEEL, COPPER, ALUMINIUM etc. |